From Rugby, Warwickshire; Went to Marlborough Secondary School; Studied at Rugby College of Engineering Technology; Worked at HM Forces - British Army; Studied at Royal School of Military Engineering; Former Maintenance Technician at International Computers Limited; Former IT Support at GlaxoSmithKline Pharmaceuticals Ltd; Lives in Letchworth

Pages

Monday, 13 July 2015

Moving on.


Dry run for fixing the layout, battens fixed to the plasterboard horizontal battens and a cantilever support beam attached to the upright brace.





Checked out the clearance for the loft ladder. 



That’s all now until I get back from The Royal International Air Tattoo.

Thursday, 9 July 2015

Man Cave PT 7.

All signed off and lighting and power installed. Now I have a workbench and shelving.







Friday, 26 June 2015

Man Cave PT 6.

Building inspection carried out and they have no issues with fixed lighting and power. So 20mm conduit fitted and two 6ft tubes installed


Started to fill it with crap!


Friday, 19 June 2015

Man Cave PT 5.



D Day +3 team arrive on site with tons of plasterboard and finished off the job. I am waiting for the building inspector to sign off the work.





Thursday, 18 June 2015

Man Cave PT 4.



D Day +2 team arrive on site with tons of CLS for the stud work for plasterboard and boxing in water tanks.







Wednesday, 17 June 2015

Man Cave PT 3



D Day +1 team arrive on site with SF19 multi-layer foil insulation




Batons fitted for plasterboard



Tuesday, 16 June 2015

Man Cave Pt 2



D Day team arrive on site with tons of timber, fitted extra joists and oodles of insulation.



All the flooring down and insulation. End of day 1